★★★★★5.0 (80+ Google Reviews)GAF Master EliteFL Licensed CCC1335262⚡ Call or Text 24/7

A GAF Master Elite Contractor’s guide to the Florida wind mitigation inspection: what the OIR-B1-1802 form records, who is allowed to complete it, and how the roof we install lines up with the features the form documents. Free roof estimate from Lionheart Roofing: 813-344-1622.

If you own a home in Florida, you have probably heard the phrase wind mitigation inspection from an insurance agent. The form behind it, OIR-B1-1802, is mostly about the roof.

This guide walks through the inspection from a roofing contractor’s side: what the inspector documents, which roof features the form records, who is allowed to complete it, and how we build so the form reflects a roof installed to current code. What any carrier does with the completed form is the carrier’s decision, and questions about your own policy go to your insurer or your insurance agent.

What Is a Wind Mitigation Inspection?

The Florida wind mitigation inspection is recorded on the Uniform Mitigation Verification Inspection Form, OIR-B1-1802. The form documents specific features of your home that affect how it holds up in high wind. It records the features; it does not award credits. Florida Statute 627.0629 requires residential property insurers to include in their rate filings actuarially reasonable discounts, credits, other rate differentials or deductible reductions for construction techniques that reduce windstorm losses. Which features qualify and what each is worth is set by each carrier’s filed rating plan, so whether any credit applies to your policy, and how much, is the carrier’s decision.

The inspection is voluntary. A new inspection replaces the prior form on file, so if the earlier form recorded a feature differently, the carrier may rate the policy differently either way. The form is a current record of the roof as built, nothing more.

Under Florida Statute 627.711, the form may be completed by a licensed home inspector with the required training, a building code inspector, a licensed general, building or residential contractor, a professional engineer, a registered architect, or any other person the insurer accepts. Lionheart does not perform the inspection. On our projects, the Wind Mitigation Inspection and Report is provided through Tampa Inspection Company, an independent third party, once the roofing project is completed and paid in full.

The 7 Categories on the Wind Mitigation Form

The OIR-B1-1802 form records seven specific home features. Most of them are about the roof.

1. Building Code

The form asks whether the home was built under the 2001 Florida Building Code or later and records the permit application date. The roof permit is how the inspector establishes the code year for the roof covering. This is why permitting your roof replacement matters: an unpermitted job cannot establish the code year the form asks for.

2. Roof Covering

Documents whether the roof covering meets the Florida Building Code requirements, and the permit date. The form records:

  • The covering type
  • The Florida product approval number for the product installed
  • The permit application date

As a GAF Master Elite contractor we install GAF architectural or designer shingles with a Florida product approval, to the manufacturer’s specification, under a permit. The form records the covering type, the Florida product approval number and the permit date, so whatever product went on the roof is what this section shows.

3. Roof Deck Attachment

Documents how the roof decking is attached to the trusses or rafters. The form records:

  • Nail size (6d or 8d; 8d ring-shank is the current Florida code standard)
  • Nail spacing along the panel edges and in the field
  • Nail pattern (6 inches on edges and in the field is the current code standard)

During a replacement we re-nail the decking to current code, 8d ring-shank nails at a 6-inch pattern, and photograph it before the underlayment goes down. Many older Tampa Bay homes were decked with 6d nails at a wider spacing; after the re-nail, the form records the current pattern.

4. Roof-to-Wall Attachment

Documents how the roof structure attaches to the walls. The attachment types the form records, in order of wind resistance from least to most, are:

  • Toe nails, nails driven at an angle through the truss into the top plate
  • Clips, metal connectors that do not wrap over the top of the truss
  • Single wraps, a single strap that wraps over the top of the truss
  • Double wraps, straps attached to the wall on both sides of the truss

The attachment is part of the framing, so a roof replacement does not usually change it, and the inspector verifies it from the attic. On older Tampa Bay homes with toe-nail construction, the form records toe nails; the rest of the form still records the roof as built.

5. Roof Geometry

Hip roofs (sloping down on all four sides) perform better in high winds than gable roofs (with vertical triangular walls at the ends). The form records whether the roof is hip, flat or other, based on how much of the roof perimeter is hip. Roof shape is not something a replacement changes, but it is documented on the form.

6. Secondary Water Resistance (SWR)

A self-adhering membrane or approved deck coating applied to the decking that resists water intrusion if the roof covering fails. The form records whether SWR is present and how it was verified, usually with photographs taken during installation, since it is covered once the roof is finished.

SWR can only be documented if it was installed and photographed before the shingles went on. We install it on the decking as part of the roof system on our replacements and keep the photographs in the job file.

7. Opening Protection

Windows, doors, skylights and garage door protection against wind-borne debris. Not roof work, but it is the seventh section of the form. The inspector records the rating of the protection on each opening.

When to Get a Wind Mitigation Inspection

After any roof replacement

A new roof changes most of what the form records: code year, roof covering, deck attachment and SWR. On our projects the inspection is scheduled through Tampa Inspection Company after completion and final payment, and you send the completed form to your insurer or your insurance agent. Whether, when and how any credit applies is the carrier’s decision.

When shopping for a new insurance policy

A form is generally valid for five years. If the one on file predates your current roof, it does not describe the roof you have now, and a new inspection records the roof as built. Ask your insurance agent whether they want a current form with the quote.

If you have received a non-renewal notice

The form gives a carrier a current record of the roof as built. Underwriting and renewal decisions are the carrier’s. Questions about a notice go to your insurer or your insurance agent.

After storm repairs

If a storm led to repairs that changed the roof covering, decking or underlayment, the form on file no longer describes the roof as it is now. A new inspection records the roof as repaired.

If your roof is 15 years old or older

Under Florida Statute 627.7011, an insurer may not refuse to issue or renew a policy on a roof under 15 years old solely because of its age. At 15 years or older, the homeowner may obtain an inspection by an authorized inspector at their own expense, and a roof shown to have at least five years of useful life remaining may not be refused on age alone. That roof-condition inspection is separate from the wind mitigation form, and it is not the free look at the roof we do when quoting a replacement. If you are already planning to replace the roof, replacing it first and inspecting afterward means the form records the new roof rather than the old one.

How We Build to the Features the Form Documents

We build every replacement so the inspector finds a roof installed to current Florida Building Code and has the documentation to record it. Here is what that means on the job.

Specifically, we:

  • Pull the permit on every replacement. The permit is what establishes the code year the form asks for.
  • Re-nail the decking to the current 6-inch pattern with 8d ring-shank nails, which is what the roof deck attachment section records.
  • Install a code-approved secondary water resistance (SWR) system on the decking before the underlayment and shingles go on.
  • Use GAF shingles with a Florida product approval, installed to the full system specification, which is what the roof covering section asks about.
  • Document everything: permit paperwork, shingle spec sheets, SWR product approvals, and photographs of the re-nailed deck and the SWR before they are covered. The inspector uses these to complete the form.
  • Provide the Wind Mitigation Inspection and Report through Tampa Inspection Company once the project is completed and paid in full. Lionheart does not perform the inspection itself.

The result is a roof built to current code and a form that records it. What any carrier does with that form is the carrier’s decision.

How to Get a Florida Wind Mitigation Inspection and Report

Steps to obtain the OIR-B1-1802 wind mitigation form after a roof replacement in Florida.

  1. Complete a permitted roof replacement to current Florida Building Code A full roof replacement to current Florida Building Code changes most of what the form records. Make sure the contractor pulls a permit, installs secondary water resistance (SWR) on the decking, re-nails the decking to the current pattern, and uses products with a Florida product approval.
  2. Have your contractor document code-plus installation Ask your contractor to keep photo documentation of the secondary water barrier, roof deck attachment, and roof-to-wall connections during the tear-off and re-nail phase. These photos support the inspector’s report.
  3. Schedule the wind mitigation inspection through Tampa Inspection Company On Lionheart projects, the Wind Mitigation Inspection and Report is provided by Tampa Inspection Company once the roofing project is completed and paid in full. They complete the OIR-B1-1802 form using photos and on-site verification.
  4. Receive the OIR-B1-1802 wind mitigation report The completed form records the building code year, roof covering, roof deck attachment, roof-to-wall attachment, roof geometry, secondary water resistance, and opening protection. It records the features; it does not award credits.
  5. Send the form to your insurer or your insurance agent Send the completed OIR-B1-1802 to your insurer or your insurance agent. Whether any credit applies, how much, and when, is the carrier’s decision under its filed rating plan. The form is generally valid for five years.

Details That Change What the Form Records

Skipping the permit

Without a permit there is no permit date and no code edition on record, so the inspector cannot establish the code year the building code and roof covering sections ask for. That stays true for the life of the roof.

Three-tab shingles

The roof covering section records the covering type, the Florida product approval number and the permit date. Whatever shingle is installed is what the form shows, under its own product approval. We install GAF architectural or designer shingles to the manufacturer’s specification.

Skipping the secondary water resistance layer

SWR is a specific product, a peel-and-stick self-adhering membrane or an approved coating applied to the decking, and standard underlayment is not SWR. If it was not installed and photographed before the roof covering went on, the form records no SWR.

Not re-nailing the decking

If the decking is not re-nailed during the tear-off, the form records the original nail size and spacing, which on many older Tampa Bay homes is 6d nails at a wider pattern. We re-nail the decking to the current 6-inch pattern with 8d ring-shank nails on every replacement.

Not asking about the inspection before signing

Before you sign a roofing contract, ask how the inspection will be handled and what will be documented during the job. On our projects, the inspection is provided through Tampa Inspection Company after completion and final payment, and the permit, product approvals and installation photographs are kept in the job file.

Frequently Asked Questions About Wind Mitigation

How much does a wind mitigation inspection cost?

Wind mitigation inspection fees vary by inspector. On Lionheart roof replacements, the Wind Mitigation Inspection and Report is provided through Tampa Inspection Company once the project is completed and paid in full. If you are arranging your own inspection on an existing roof, ask the inspector for their fee when you book.

Can I get a wind mitigation inspection on my current older roof?

Yes. The form records what is actually installed: the code year of the permit, the roof covering, the deck nailing, the roof-to-wall attachment, the roof shape, SWR if it is present and documented, and opening protection. On an older roof the inspector records the older features. If you are already planning to replace the roof, replacing it first and inspecting afterward means the form records the new roof.

Does every Florida homeowner qualify for wind mitigation credits?

Florida Statute 627.0629 requires residential property insurers to include in their rate filings actuarially reasonable discounts, credits, other rate differentials or deductible reductions for construction techniques that reduce windstorm losses. Which features qualify, what each is worth, and whether any credit applies to a particular policy is set by each carrier’s filed rating plan and decided by the carrier. The inspection records the features; your insurer or your insurance agent can tell you how your policy treats them.

How long is a wind mitigation report valid?

A wind mitigation form is generally valid for five years from the inspection date. A roof replacement or storm repair changes what the form describes, so a new inspection after that work records the roof as it is now. A new form replaces the prior one on file.

Will a new roof automatically improve my wind mitigation credits?

A new roof changes what the form records, not what a carrier does with it. A permitted replacement with SWR, decking re-nailed to the current pattern, and shingles with a Florida product approval is recorded that way. An unpermitted replacement has no code year to record, and if SWR was not installed and photographed the form records none. A new form replaces the prior one on file, and if the earlier form recorded a feature differently, the carrier may rate the policy differently either way.

Can I request a wind mitigation inspection from my current roofer?

Lionheart does not perform wind mitigation inspections. On our roof replacements, the Wind Mitigation Inspection and Report is provided through Tampa Inspection Company, an independent third party, once the project is completed and paid in full. Ask any contractor how they handle the inspection before signing.

What if the inspector recorded a feature wrongly?

The inspector records the features. If you believe a feature was recorded wrongly, for example SWR that was installed and photographed but not noted, ask the inspector to review it against the documentation from the job file. What the carrier does with the form is the carrier’s decision.

How does wind mitigation affect insurance non-renewal?

The form gives a carrier a current record of the roof as built. Underwriting and renewal decisions are the carrier’s. Questions about a notice go to your insurer or your insurance agent.

Get a Roof Replacement Built to Current Code

Lionheart Roofing is a locally owned GAF Master Elite Contractor serving Tampa, Brandon, Valrico, Riverview, Lithia / FishHawk, Wesley Chapel, Sun City Center, Apollo Beach, and communities across Tampa Bay. Every replacement we install is built to the features the OIR-B1-1802 form documents: GAF shingles with a Florida product approval, secondary water resistance on the decking, 8d ring-shank re-nailing at a 6-inch pattern, a pulled permit with the code documentation, and the Wind Mitigation Inspection and Report through Tampa Inspection Company once the project is completed and paid in full.

The result is a roof built to current Florida code, and an OIR-B1-1802 form that records it.

We respond within one business day.

Related reading: How much does a shingle roof replacement cost in Florida? | Florida Roof Insurance Claim Guide | What GAF Master Elite means for Florida homeowners | How to choose a Tampa Bay roofing contractor | Shingle vs metal vs tile: Florida material guide | My Safe Florida Home guide